On 10/13/15, 1:13 PM, "dev on behalf of Marvin Addison" <dev-bounces at shibboleth.net on behalf of marvin.addison at gmail.com> wrote:
>
>I really want functional SLO to make the release, and the 19th is an ambitious target date for that. Scott raised some concerns about that date as well, so what about the following week, the 26th?
I probably can make a freeze that week, or at least a "bug fixes arising from testing only" situation, but I'll know more next week once I see the SPNEGO code.
I don't know what state we're in wrt to SLO, I really haven't had time to look at that work in progress.
Brent's delegation work is the other basically must-have for this release.
I would like to shoot for releasing at least a couple of weeks before Thanksgiving, but I guess if we slip even that far, it probably doesn't matter much.